December 2022
Roof completed, church opening created to Assisi, office space insulated and drywall installed, gas service connected, fire suppression system roughed in throughout building, and external brick fascia completed.
January 2023
Plumbing and HVAC to lower level, roofing and siding completed, upper-level windows set, lower-level insulation and dry wall installed.
February 2023
Upper-level ceiling installed followed by painting and flooring. Elevator to be installed and inspected. Kitchen floor installed.
March 2023
Placement of open office furniture. Lower-level walls and ceilings painted, building systems certified, partial placement of kitchen equipment.
April 2023
Wood wainscoting in the main hall, installation of doors and cabinets, lower-level flooring and audio/visual equipment installed.
May 2023
Final clean-up and touch-up of all finishes, delivery of additional furniture and equipment, exterior walks and curbs completed, final landscaping. Receipt of Certificate of Occupancy.